March 7 set as completion date for jail

By Jessica LeDuc
Blade staff writer


 The end of construction may finally be in sight for Cloud County's new Law Enforcement Center and Jail.
 Cliff Sullivan and Rick Morton with Goldberg, Sullivan and McCrerey, and Jody Cotton, construction superintendent with Zahner Hansen Construction Group met with Cloud County commissioners Monday afternoon to provide an update on the project.
Cotton said he is shooting for a March 7 date for the project to be substantially completed.
 "We should be able to meet that March 7th date," Cotton told commissioners. "I'm doing everything I can to bring it to a completion by then."
The jail was scheduled to be completed nearly six months ago. In August 2012, Zahner Hansen Construction Group of Brentwood, Tenn., was awarded the project to construct the new law enforcement center and jail. Construction on the $5.9 million, 80-bed jail and sheriff's offices began in the winter of 2012.
Sept. 17, 2013, was the originally contracted substantial completion date for the Center, but a number of issues, including an electrical subcontractor briefly walking off the job, have resulted in numerous delays.
 On April 1, the commission must make the first bond payment of $117,300, which represents the interest on the bond.
 Cotton told commissioners the main hurdle to overcome in completing the facility is a design issue and documentation problem with the fire alarm system. After a walk-through last week by the state fire marshal, Concordia Fire Chief Eric Voss, and Concordia Building Inspector Bruno Rehbein, Cotton said a problem with the smoke evacuation system was found. Should a fire start in the jail, a smoke evacuation system is in place to remove smoke from the cell pods. Currently, there is a conflict between the HVAC and electrical contractors as to who was responsible for completing the electrical work for that system.
 Cotton said if that conflict is not resolved by Wednesday, he has workers ready to come in and finish that portion of the project. He also said he planned to talk to Rehbein in the hopes of receiving a temporary certificate of occupancy so sheriff's department staff can begin to move into the administrative portion of the facility.
Painters will be coming in this week to work on touch-ups, Cotton said, and final cleaning will be happening at the same time.
Once it is ready for occupancy, the commissioners plan to have an open house so the public can view the facility before prisoners are housed. By Jessica LeDuc
Blade staff writer

 The end of construction may finally be in sight for Cloud County's new Law Enforcement Center and Jail.
 Cliff Sullivan and Rick Morton with Goldberg, Sullivan and McCrerey, and Jody Cotton, construction superintendent with Zahner Hansen Construction Group met with Cloud County commissioners Monday afternoon to provide an update on the project.
Cotton said he is shooting for a March 7 date for the project to be substantially completed.
 "We should be able to meet that March 7th date," Cotton told commissioners. "I'm doing everything I can to bring it to a completion by then."
The jail was scheduled to be completed nearly six months ago. In August 2012, Zahner Hansen Construction Group of Brentwood, Tenn., was awarded the project to construct the new law enforcement center and jail. Construction on the $5.9 million, 80-bed jail and sheriff's offices began in the winter of 2012.
Sept. 17, 2013, was the originally contracted substantial completion date for the Center, but a number of issues, including an electrical subcontractor briefly walking off the job, have resulted in numerous delays.
On April 1, the commission must make the first bond payment of $117,300, which represents the interest on the bond.
 Cotton told commissioners the main hurdle to overcome in completing the facility is a design issue and documentation problem with the fire alarm system. After a walk-through last week by the state fire marshal, Concordia Fire Chief Eric Voss, and Concordia Building Inspector Bruno Rehbein, Cotton said a problem with the smoke evacuation system was found. Should a fire start in the jail, a smoke evacuation system is in place to remove smoke from the cell pods. Currently, there is a conflict between the HVAC and electrical contractors as to who was responsible for completing the electrical work for that system.
 Cotton said if that conflict is not resolved by Wednesday, he has workers ready to come in and finish that portion of the project. He also said he planned to talk to Rehbein in the hopes of receiving a temporary certificate of occupancy so sheriff's department staff can begin to move into the administrative portion of the facility.
Painters will be coming in this week to work on touch-ups, Cotton said, and final cleaning will be happening at the same time.
 Once it is ready for occupancy, the commissioners plan to have an open house so the public can view the facility before prisoners are housed.

NEWS

Courthouse 4-24-14

District Court CIVIL Denied The request of Bryan Douglas Sprung, Hutchinson Prison, for an appointed attorney was denied and his motion for relief pursuant to K.S.A. 6-1507 was denied. Settled: American Express Centurion Bank received a judgment of $3,517.88 and costs from Carroll... [More]

For the record 4-24-14

Police Dept. Report Accident—Officers investigated an Accident at 8:10 p.m., April 23, in the 300 block of West 16th involving a vehicle driven by Thomas Pudge, Delphos, and a vehicle owned by David Redmond, Concordia. Arrest—Officers arrested Amber Wogomon, 23, Concordia,... [More]

For the record 4-23-14

Police Dept. Report Damage to property—Darci J. Elliott, Concordia, reported Damage to Property at 7:35 a.m., April 22. Damage occurred sometime in the last 48 hours in the 400 block of West 16th St. Fire Dept./EMS Report At 9:12 p.m., Tuesday, Medic-5 responded to the... [More]

More News

SPORTS

Alexander signs with Eckerd College

Cloud County Community College sophomore Jordyn Alexander has signed to play basketball at Eckerd College in St. Petersburg, Fla. Alexander led Cloud County in scoring (16.4) and rebounding (7.9) this past season. She shot a team best 54.7 percent from the field and 41.2 percent... [More]

Trobee leads T-Birds to rout of Brown Mackie

SALINA – Kylie Trobee scored three runs and drove in four in the Cloud County Community College softball team's 18-0 win over Brown Mackie here yesterday. The win completed a doubleheader sweep; the T-Birds won game one 13-0. Cloud County got started early in the finale... [More]

More Sports

OPINIONS

Letter to the Editor 4-18-14

Dear Editor,   Questions that need answers? 1. Why should we sign up for the Special Civility Pledge? 2. Isn't the “Bill of Rights” still acceptable?        3. Aren't the Ten Commandments still taught? 4. What happened to the... [More]

More Opinions

Buy Photos